Markham, ON

Material
Concrete foundation sections with light rebar
Volume
58 tonnes
Service
Full-day concrete crushing
Result
Recycled concrete aggregate used for backfill and site grading
Time
8 hours

Project Summary

A demolition contractor prepared the concrete before our arrival and loaded the crusher using their excavator. Metal reinforcement was separated during processing.

Mississauga, ON

Material
Old concrete patio slabs and walkway sections
Volume
24 tonnes
Service
Minimum service call
Result
Reusable granular base for a replacement patio
Time
3.5 hours

Project Summary

The removed slabs were stockpiled near the driveway with sufficient access for the crusher. The processed material remained on-site for the landscaping contractor.

Toronto, ON

Material
Backyard concrete patio and broken retaining-wall blocks
Volume
20 tonnes
Service
Full-service crushing
Result
Recycled base material for new interlock installation
Time
Full-service day

Project Summary

The property had limited access and no equipment available to load the crusher. Material handling support was provided as part of the service.

Richmond Hill, ON

Material
Clean concrete from a garage floor replacement
Volume
36 tonnes
Service
Half-day concrete crushing
Result
Processed aggregate reused beneath the new garage slab
Time
5 hours

Project Summary

The contractor prepared manageable concrete pieces and loaded the crusher with a compact excavator. Nearly all processed material was reused within the project.

Brampton, ON

Material
Mixed driveway and curb concrete with wire mesh
Volume
64 tonnes
Service
Full-day concrete crushing
Result
Recycled aggregate for access-road construction and backfill
Time
8 hours

Project Summary

The pile contained sections of wire mesh that required additional sorting. The contractor supplied loading equipment and separated exposed metal during processing.

Caledon, ON

Material
Fieldstone collected during property excavation
Volume
46 tonnes
Service
Stone and rock crushing
Result
Crushed stone used for drainage and rural driveway maintenance
Time
Full day

Project Summary

Large stones were pre-broken before processing. The resulting material was distributed across drainage areas and a private gravel driveway.

Newmarket, ON

Material
Concrete pool deck and landscaping slabs
Volume
28 tonnes
Service
Half-day crushing
Result
Recycled material used as structural fill around the renovated pool area
Time
5 hours

Project Summary

The concrete was removed and prepared before arrival. Crushing on-site helped avoid multiple disposal-bin loads and reduced the amount of new fill required.

Pickering, ON

Material
Commercial sidewalk and concrete curb sections
Volume
72 tonnes
Service
Full-day contractor support
Result
15–40 mm aggregate reused as sub-base for a parking-area repair
Time
8 hours

Project Summary

The general contractor provided an excavator and operator. Crushing was coordinated with the demolition schedule so the processed aggregate could be used immediately.

Ajax, ON

Material
Concrete from a residential addition and old foundation wall
Volume
42 tonnes
Service
Full-service concrete crushing
Result
Recycled aggregate used for foundation backfill and temporary site access
Time
Full-service day

Project Summary

The customer required both crushing and material handling. The finished aggregate was placed in separate areas for backfill and temporary construction access.

Whitby, ON

Material
Excavated limestone and large landscaping stones
Volume
50 tonnes
Service
Stone crushing
Result
Drainage stone and general-purpose granular material
Time
Full day

Project Summary

The stone was generated during grading work for a new residential property. Oversized pieces were reduced before entering the crusher.

Oshawa, ON

Material
Warehouse floor concrete with light reinforcement
Volume
42 tonnes
Service
Full-day commercial crushing
Result
Recycled aggregate used as compacted fill inside the renovated building
Time
Full day, with remaining material completed during a second visit

Project Summary

The project was completed in coordination with the demolition contractor. Prepared material was processed in stages to avoid interrupting other work on the site.